FS#15218 — G103B21, G106A09, G107B02, G113B24, G114A02, G114A03, G114A06, G107B05, G107B09, G107B10, G113A06, G
Attached to Project— Network
Modernization | |
Gravelines → GRA-1 | |
CLOSED | |
![]() |
Summary: As we are continuously improving the quality of our systems, we will be upgrading our public facing network equipment to a superior model
Actions: Replace the public network device.
Start: 12/10/2017. starting at 10:00 PM (UTC +02)
Affected racks: G103B21, G106A09, G107B02, G113B24, G114A02, G114A03, G114A06, G107B05, G107B09, G107B10, G113A06, G113B25, G113B23
Impact: One disconnection of about one minute of the public network.
This task will be updated regularly during the maintenance
Date: Monday, 11 December 2017, 20:06PMActions: Replace the public network device.
Start: 12/10/2017. starting at 10:00 PM (UTC +02)
Affected racks: G103B21, G106A09, G107B02, G113B24, G114A02, G114A03, G114A06, G107B05, G107B09, G107B10, G113A06, G113B25, G113B23
Impact: One disconnection of about one minute of the public network.
This task will be updated regularly during the maintenance
Reason for closing: Done
The migration of the network equipment began for racks G103B21, G106A09, G107B02, G113B24, G114A02, G114A03, G114A06, G107B05, G107B09, G107B10, G113A06, G113B25, G113B23
Further to technical concerns the migration of racks : G113B25 and G113B24 is cancelled.
The migration of racks : G103B21, G106A09, G107B02, G114A02, G114A03, G114A06, G107B05, G107B09, G107B10, G113A06, G113B23 is ended.